Watch to learn setting out a building foundation using the 3-4-5 method.
__________________________________________
BUY ME A COFFEE: https://paystack.com/pay/buildproglob...
If the video was helpful to you, and you want to help me keep creating, please consider buying me a coffee. It's a small gesture, but it means a lot to me. The money I earn will go towards things like data subscription, my website hosting, software subscriptions, and marketing costs.
Follow this link to buy me a coffee: https://paystack.com/pay/buildproglob...
Thank you for your support!
___________________________________________
Do you need private coaching on using AutoCAD for producing Building Drawings? Click this link: https://www.fiverr.com/s2/d5e7c2a15b to buy my Gig on Fiverr.
Do you want Building and/or Structural Drawings produced for you? Click this link: https://www.fiverr.com/s2/3fbbf51c7c to buy my Gig on Fiverr.
____________________________________________
VIDEO CONTENT:
Setting out is the process of marking out foundation trenches, column pits, and other important points of a building on the ground for excavation and construction purposes. You will learn the procedures of setting out a building foundation using the 3-4-5 method.
STEP ONE: SITE CLEARANCE
Site Clearance involves clearing a site of machines and dangerous materials as well as leveling and preparing the ground for any upcoming building or landscaping projects.
Proper site clearance is necessary to ensure the safety of all workers and anybody else who may be present on the property.
STEP TWO: POSITION THE BUILDING
The approximate location and orientation of the building should be determined by measuring the required setback as shown on the site plan drawing.
The site plan is typically included in a set of Architectural Drawings.
STEP THREE: ESTABLISH BASE POINT
Choose one of the building's corners you want to start with.
Drive a peg (wooden or steel) into the ground at the angle or corner you've decided to use as your base point (let's name this point A).
Drive a peg (wooden or steel) into the ground at the angle or corner you've decided to use as your base point (let's name this point A).
If you're using a wooden peg, drive a nail on top of it. When using steel pegs, there is no need for nails.
STEP FOUR: SET OUT THE RIGHT ANGLE OF THE BUILDING
Tie a building line on the steel peg or nail on the wooden peg and move along the baseline of the building making a straight line.
Measure 3 meters (from point A) along the straight line (let’s call this point B).
Then measure another 4 meters away from the first point (Point A) forming a right angle (let’s call this point C).
Use the measuring tape to confirm that the distance between point B and C is 5 meters.
Note that the straight line from point A to B remains the same, you only shift the other line (point A to C) to form the right Angle.
STEP FIVE: ESTABLISH THE FOUR CORNERS OF THE BUILDING
Similarly, using 3-4-5 method, establish all the four corners and perimeter of the building.
Now that the four corners of the building has been established, the next thing to do is to set up the profile boards.
STEP SIX: ESTABLISH THE PROFILE BOARDS
These should be about 1200mm (2ft) away from the already established four corners and perimeter of the building.
STEP SEVEN: NAIL POINTS OF EXCAVATION ON THE PROFILES
These should be about 1200mm (2ft) away from the already established four corners and perimeter of the building.
Nail and mark out spots on the battens for foundation trench excavation. The opposing side should be done in the same way.
Tie the building line to the opposing sides of the profile boards and mark the excavation areas on the ground according to the Structural Drawings.
Then excavate the foundation trenches, making sure everything is level.
When the foundation trench excavation is complete, the next step is to remove the line and nail another point to set points for column pit excavation.
If you're using out to out, make sure you use it all the way through, and if you're using in to in, make sure you use it all the way through. Your Column Placement will be where your lines intersect.
____________________________________________
SUBSCRIBE: https://www.youtube.com/channel/UCRPA...
Facebook:   / buildproglob.  .
Instagram:   / buildproglo.  .
Email: [email protected]
Phone/WhatsApp: +2347018320501

Комментарии

Информация по комментариям в разработке