Recently, the Ministry of Public Works and Transport (MPWT) posted on its official Facebook page the detailed status of the main road network that has been built and is being upgraded in four provinces in the development zone. Triangle CLV.
Indeed, the construction of roads to less developed areas, especially the border area, is the goal of the Royal Government of Cambodia. Residents there say that the construction of roads along the border, which previously did not have roads, people want to travel from one village to another, have to ask for access through Vietnam. But after the border ring road, people can travel from one village to another without having to ask for access through Vietnam. Samdech presented the progress of the construction of the border ring road in the northeastern provinces, in which Kratie province has completed the construction of the border ring road, while the people of Kratie, Stung Treng, Mondulkiri and Ratanakkiri provinces will be connected through this border ring road through the Department The engineering of the Ministry of National Defense must work hard to continue to build the border ring road to reach the area of ​​the three corners of the dragon tail in the future.
Below I will highlight the seven road networks that connect the northeastern provinces of Cambodia, including the following:

1. Section of National Road 78
Achievements of the National Road 78 from Banlung to Stung Treng Provincial Border
Length: 56.12 km
Width: 11 meters
Starting point: km 65 + 080 (border of Stung Treng and Ratanakkiri provinces), village 3, Sre Angkor commune, Kon Mom district, Ratanakkiri province.
End point: km 121 + 200 (Wat Phnom Svay), Sangkat Boeung Kanseng, Banlung city
Road type: DBST
2. National Road Project No. 76
National Road 76 is an important economic artery for our Cambodian people, especially those in Mondulkiri to facilitate the transportation of agricultural products to the market.
National Road 76 project
Length: 49.10 km
Starting point: PK00 + 000 Snoul village, Snoul commune (Snoul roundabout), Kratie province.
End point: PK49 + 100, Kronhong Sen Chey II village (Mondulkiri border)
Road type: DBST
Restoration: 2007
Construction completed: 2011
Achievement percentage: 100%
This section of National Road 76 does not end in Mondulkiri, but it extends to Ratanakiri, which has
Total road length: 60.73 km
Road type: DBST
Starting point: km 234 + 420 (border of Mondulkiri and Ratanakkiri provinces), Chey Udom commune, Lumphat district, Ratanakkiri province
End point: km 295 + 150 (intersection of National Road No. 78 at km 122 + 700) Ta Ang Kate village, Ta Ang commune, Kon Mom district, Rattanakiri province.
3. Kratie Mekong River Bridge Construction Project and Connected Road (National Road No. 60B)
Kratie Mekong River Bridge Construction Project and Connected Road (National Road No. 60B)
Starting from PK76 + 120, Kampong Thom border to PK117 + 790, Tiger Roundabout (P.D.
Length: 41.67 km AC rubber mat
Restoration: January 2, 2023
Completion: September 25, 2026
Achievement percentage: 44.31%
4. National Road 7 Project
National Road Construction Project No. 7
Length: 198.10 km
Starting point: Tbong Khmum-Kratie provincial border (Chiv bridge)
End point: Kratie-Stung Treng border (Ochralang)
Road type: AC pavement
Restoration: June 1, 2018
Construction completed: August 2024
Achievement percentage: 97%
5. National Road 74 Project
There are projects to build National Road 74
Length: 21.28 km
Starting point: Kbal Trach village, Sre Char commune, Snoul district
End point: Trapeang Sre village, outside 2 Thnou commune (Cambodia-Vietnam border)
Road type: DBST
Restoration: 2007
Construction completed: 2009
Achievement percentage: 100%
6. National Road Project No. 78-5
Construction of National Road No. 78-5 from Banlung to Ta Veng!
Length: 21.95 km
Starting point: From the junction of National Road No. 78 (km 123 + 250), Sangkat La Ban Siek, Banlung City, Ratanakkiri Province.
End point: km 21 + 950, Svay village, Poy commune, O'Chum district
Road type: DBST
During a special message related to the CLV development triangle on July 23, 2024, Samdech Techo Hun Sen stated, "I hope that the Royal Government will continue its efforts to build National Road 78.5 from the city. "Ratanakkiri province is still at three angles, and at that time, I, Your Majesty, I hope that I, Your Majesty, am alive and will travel there."

7. Provincial Road Project No. 377!
Understand the achievements of Provincial Road Project No. 377!
Length: 48.59 km
Starting point: (White Dove Circle) Trapeang Pring Village, Sangkat Kratie, Kratie City
End point: Sambo commune, Sambo district
Road type: AC pavement
Restoration: April 4, 2023
Construction completed: December 2024
Achievement percentage: 68.7%