Outstanding progress is visible across every major sector of Spotify Camp Nou as multiple key developments unfold simultaneously.
Concrete panels have officially arrived for the Tribuna elevator shaft structures — a huge step toward enclosure phases. Upper beam coating continues while chrome tubes remain heavily staged across multiple levels.
At the diamond commercial zones, glass panel installation is RESUMING at the official store after nearly a week of inactivity. Suction equipment is positioned, panels are staged, and crews are ready to complete the missing corner and entrance sections.
The South Goal area shows active concrete pumping near the VIP zone, advancing elevator structures, and continued sandwich panel enclosure progress. Corner slat installation is accelerating with one sector now fully complete.
Major news in the Lateral section: two new scaffolding towers have been erected in upper cantilever zones — a strong indicator that another radial beam installation is approaching. The fifth compression ring pillar has arrived and is staged, preparing the next structural milestone.
At the North Goal corner, new chrome tube levels are being installed, drainage tubes are arriving, emergency exit doors are now in place, and structural finishing continues.
The rebuild is accelerating across structural, façade, and enclosure phases — and the stadium transformation is becoming more dramatic every week.
👍 Like the video
🔔 Subscribe to MegaVerse Builds for daily Camp Nou construction updates
💬 Comment your thoughts below
MegaVerse Builds — Where Every Pour Counts.Outstanding progress is visible across every major sector of Spotify Camp Nou as multiple key developments unfold simultaneously.
Concrete panels have officially arrived for the Tribuna elevator shaft structures — a huge step toward enclosure phases. Upper beam coating continues while chrome tubes remain heavily staged across multiple levels.
At the diamond commercial zones, glass panel installation is RESUMING at the official store after nearly a week of inactivity. Suction equipment is positioned, panels are staged, and crews are ready to complete the missing corner and entrance sections.
The South Goal area shows active concrete pumping near the VIP zone, advancing elevator structures, and continued sandwich panel enclosure progress. Corner slat installation is accelerating with one sector now fully complete.
Major news in the Lateral section: two new scaffolding towers have been erected in upper cantilever zones — a strong indicator that another radial beam installation is approaching. The fifth compression ring pillar has arrived and is staged, preparing the next structural milestone.
At the North Goal corner, new chrome tube levels are being installed, drainage tubes are arriving, emergency exit doors are now in place, and structural finishing continues.
The rebuild is accelerating across structural, façade, and enclosure phases — and the stadium transformation is becoming more dramatic every week.
👍 Like the video
🔔 Subscribe to MegaVerse Builds for daily Camp Nou construction updates
💬 Comment your thoughts below
MegaVerse Builds — Where Every Pour Counts.
🔴 COPYRIGHT DISCLAIMER
MegaVerse Builds does not claim ownership of all footage featured in this video. All rights belong to their respective owners. Certain clips are credited to EspaiHector. Content is used under Section 107 of the Copyright Act 1976, which allows “fair use” for purposes such as commentary, criticism, news reporting, teaching, and research. No copyright infringement is intended.
🎥 Footage Credit: EspaiHector
📩 If you are the rightful owner of any footage used and would like credit, modification, or removal, please contact us directly via email (preferred) or leave a comment, and we will respond promptly.
#CampNou #SpotifyCampNou #CampNouUpdate #StadiumConstruction #FCBarcelona #MegaVerseBuilds #RadialBeam #CompressionRing #Barcelona #FootballStadium
Информация по комментариям в разработке