Operations Management: Project Management – Crashing III

Описание к видео Operations Management: Project Management – Crashing III

This problem walk-though video will demonstrate how to crash a project after determining drawing the network diagram and determining the critical paths.

NOTE:
From 7:09 to 10:23 there is a typo in some of the columns relating to Path 3:

The Blue Wave 1 column should read –1=19

The Green Wave 2 column should read -2=17

The Orange Wave column should read –1=16

These were actually corrected at 10:24 going forward.

Those typos do not change the final crash results and costs.