GDC completed the construction of a 25 Kilometre Steam Gathering System (SGS) in the Menengai Geothermal Project. The SGS will be used to collect steam from Menengai production wells and deliver them to the Power Plants, currently being constructed by Independent Power Producers (IPPs), contracted by GDC. In Baringo-Silali Geothermal Project, GDC continues with its exploration drilling. The Company has also completed the construction of a robust water infrastructure, of over a hundred kilometres, to support drilling activities in the area, as well as for Community use.