#4 Contract Costing - Work Uncertified Not Given - Problem 3 - B.COM / CA INTER - By Saheb Academy

Описание к видео #4 Contract Costing - Work Uncertified Not Given - Problem 3 - B.COM / CA INTER - By Saheb Academy

This is the illustration 5 of the CA Inter study material. Here there is a hidden adjustment i.e. Work Uncertified exists but it's value is not given so we have to calculate it.

Here in this contract Plant is also used for 146 days in a year so we have to apportion the depreciation.

CA Inter students have to solve this problem by making two sections.

IPCC and B.Com students have to solve this problem by making three sections since you also have to split notional profit into Costing P&L and WIP Reserve.

This is very important question from the exam point of view.

Contract Costing Playlist
   • Contract Costing - B.COM / CA INTER  

Join SILVER CLUB to get access to PREMIUM VIDEOS:
   / @sahebacademy  

This is for the students of B.COM, BBA, CA INTER, CMA and any other accounting courses which has this chapter in its syllabus.

PDF Notes (Telegram)
https://t.me/sahebacademy7

Material Costing Playlist
   • Material Costing - B.COM / CMA / CA I...  

Labour Costing Playlist
   • Labour Costing - B.COM / CMA / CA INTER  

Clear your doubts by direct messaging us on Instagram
  / sahebacademy  

Please Like, Subscribe and Share this video on your social media account.

#CostAccounting #BCOM #CAINTER

Комментарии

Информация по комментариям в разработке