Live Construction Planning Discussion where we discussed the following topics:

Mechanical Engineering Background I had completed the Primavera P6 Course in India. but till now am not getting Job as a Planning engineer please suggest
Very common issue. Making PV=EV while creating a revised schedule. (Without splitting activities). What is the way?
kindly explain the difference between the longest path and the critical path? plz. I am confused
Do you have a free training session but less fee on the certificate?
what is the concurrent delay?
How to reduce total float in a schedule?
Master's Degree useful or not
we need ur opinion about BIM please can u advise us, thnx a lot sir
Can you explain for us deferences between progress tracking based on unit one time or cost loaded one time?
how to become advanced in excel?
Sir how to track a project with actual quantity in ms project?
If there is multiple longest path what is the method for showing each path separately?
how can I register for your paid course, any details pls?
PMI -SP OR AACE PSP?
Hi. when there is concurrent delay what we should do? can we say that we should calculate them as client delays?
What is the difference between a recovery schedule and a revised schedule?
I am a quantity surveyor by profession but I want really to be a planning engineer and what can you advise to me. I already started learning Primavera P6. How can I enter into a planning career?
Sir, How to get wbs activities extracted for multiple packages. Like there are 10 packages and if I want to get only engineering wbs and its activities how to get the same in primavera?
what good steps to preparing a revised program schedule
what are the new software and tools planners need to learn for the next decade?
I am QC in civil engineering roads and buildings for 4 years. I am planning to move into a planning Career. what is ur advice?
what's the best way to represent the relationship between concrete formwork and fixing steel, considering fixing steel may start 2day after the start of formwork, and formwork should end after the end of fixing steel.
what's the best way to get an actual link with the plan !? by mean I wanna know how can I get the best KPI from my team !?
If I register for your courses, can I enter the course contents for a limited time or lifelong?
front loading and backloading
What is the difference between retained logic & override logic?
dear, can you please tell me how can I load resources from my BOQ to primavera?
Sir, please tell me how can I check all links that I have done in planned are right?
can I make the same cost loading in your video of cost loading? can I load all resources using vlookup?
What is the use of the Level of effort and WBS summary activity type?
What is the use of % complete type? There are three methods? 1. Duration 2. Physical 3. Units
What are the better options as per your experience for scheduling the progressed activities? In Retained logic ve Progress override?
if the free float consumed of activities would that activities be critical??
How to check the schedule after preparation?
Hi Eng.Hany, What Do You Prefer Duration Percentage Complete or Physical?

Keep in Touch

Twitter:   / planningeest  
YouTube:    / planningengineernet  
Linked in:   / planning-engineer-est  
Instagram:   / planningengineerest  
FaceBook:   / planningengineerdotnet  
WhatsApp: +201277767728
Email: [email protected]

Комментарии

Информация по комментариям в разработке