Metro Manila Skyway Stage 3 update as of November 2019

Описание к видео Metro Manila Skyway Stage 3 update as of November 2019

This is our update no. 69 for the #SkywayStage3 series we have been documenting ever since it started. Sorry for the late release of this video as we have waited for a scheduled precast coping beam installation and we wanted to see in person how it is being done with the new method approved by both NLEX and Skyway team. Thank you to all the people who have been waiting and messaging about the update, dont worry about the updates, will always and will try to post a monthly update for this channel. This is why this channel continue to exist, because of Skyway :-)
(As requested by other viewers we shot the entire update within the month of November.)

Lets start shall we?
1:16 - We could see the toll plaza of Gil Puyat off ramp SB as of this month
2:16 - check out the status of the Quirino Offramp , on the base portion or landing as others called we could see the road is divided into two... 2:35 it seems there is a provision (the right side) going somewhere... now this is very interesting and lets see how this ends up.
3:32 Section 2A PORTION Plaza Dilao
4:20 - Nagtahan Offramp developments
5:35 - Tomas Claudio area - very busy indeed many cranes and pile boring activities. A portion of Laura street was closed to public traffic , this is one of the remaining critical portions of the main line of #MetroManilaSkywayStage3
8:12 - Section 2B portion - Span 2 upper deck connected and see the developments
10:17 - Lubiran bridge portion
11:53 - now this portion of San Juan river has progress, see the ub girders installed comparing to last month's update.
12:59 - Girders installed along this portion of San Juan river, its getting closer to the old sta mesa san juan bridge
13:18 - pouring has been done on this portion. This is in comparison to my last months update
14:21 - The Aurora blvd On ramp - hope the ROW issue will be resolved here and the re alignment of utilities
14:53 - The E Rod Offramp SB - in front of INC church a ramp will be made.
16:53 - The Quezon Avenue on and offramps progress
20:05 - Section 4 - Araneta - delmonte portion up to Sto Domingo - this is also one of the remaining portions that i am observing. Still a little bit long way to go, hope all the relocation activities of utilities are done
21:33 - Sgt Rivera area - girders have been installed and more span have been poured but hope they can go faster.
24:04 - I guess two more span and this portion will be connected to the main line along A bonifacio

25:04 - Section 5 Balintawak area On 25:30 see the column almost beside the Edsa overpass? That will be a very tall column to be able to bypass the LRT and Edsa overpass
26:09 - Precast coping beam installation on NLEX, this is what i wanted to see. The actual installation of the precast coping beam and was lucky to witness this. NLEX traffic was stop when the precast coping beam was lifted and turned.
30:15 - NLEX Eternal Gardens portion
Special thanks to
Mr Ravelo Fronda
Engr Pasky
Mr. Ramon Guico
Mr Jerome
Mr Sherman Ngo
Mr Jonathan Yu

Thank you very much to SMC Tollways

Комментарии

Информация по комментариям в разработке