Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || AUG 2024

Описание к видео Bangalore Metro || Blue Line || Phase 2B || Airport to Hebbal || AUG 2024

Blue line updates from Airport to Hebbal. Recorded Date : 10-AUG-2024

Phase 2B - Airport to Hebbal

***********************************************
AUGUST 2024 Updates

Civil Contractor : PKG2 - NCC LTD - 11.678 KM
PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion.

Piling Works Happening and Pier casting Picking up pace.

Package 2 :
Kodigehalli Station :- RHS Pier casting in Progress. LHS Piling completed.
Jakkur Cross Station :- CC Beam casting in Progress.
Jakkur Plantation Station : Unsure
Yelahanka / Kogilu Cross Station :- Beam casting for Concourse and Platform in progress
Bagalur Cross Station : U girder Done. Concourse i-girders done. Platform i-giders in progress

Package 3 :
Bettahalasuru Station : Unsure
Chikkajala Station : Pier casting is in progress
Doddajala Station : Beam casting for Concourse and Platform in progress

Stations done by KIAL :
Airport City Metro Station : Civil Works have begun.
Airport Terminal Metro Station : Civil works complete. Finishing works pending

ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಕೆ.ಆರ್‌.ಪುರ ನಿಂದ ಕೆಂಪೇಗೌಡ ಅಂತರ್ ರಾಷ್ಟ್ರೀಯ ವಿಮಾನ ನಿಲ್ದಾಣ | ಏರ್ಪೋರ್ಟ್ ಮೆಟ್ರೊ ಎರಡನೇ ಹಂತ–2B


––––––––––––––––––––––––––––––
Track: Joy — Next Route [Audio Library Release]
Music provided by Audio Library Plus
Watch:    • Joy — Next Route | Free Background Mu...  
Free Download / Stream: https://alplus.io/joy
––––––––––––––––––––––––––––––

Комментарии

Информация по комментариям в разработке