Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: JUN 2024

Описание к видео Bangalore Metro : Blue line : Airport line : Hebbal to Tin Factory: JUN 2024

Blue line updates from Hebbal to Kasturinagar. Recorded Date : 09-JUN-2024

Phase 2B - Hebbal to K R puram

***********************************************

JUNE 2024 Updates

Civil Contractor : PKG1 - NCC LTD - 11.003 KM & 650 metr depot line
PKG2 - NCC LTD - 11.678 KM
PKG3 - NCC LTD - 15.011 KM including 718 meter cut and cover portion.

Piling Works Happening and Pier casting Picking up pace.

Stations in the stretch :

Package 1 :
Kasturinagar Station - Pier casting Upto Concourse level in Progress.
Horamavu Station - All piers cast up to concourse level.
HRBR Layout Station - Concourse Arm Connector affixing has begun.
Kalyan Nagar Station - Concourse Arm Connector affixing has begun.
HBR Layout Station - Pier casting in progress.
Nagavara Station ( Interchange with Pink Line ) - Piling In Progress.
Veerannapalya Station - RHS : Pier casting. LHS : Piling.
Kempapura Station - Median Pier rebar up. Side Pier works yet to begin.
Hebbal Station - Pier casting yet to begin.