Set-up a Primavera P6 layout to highlight activities that are behind schedule on the Gantt chart.

Описание к видео Set-up a Primavera P6 layout to highlight activities that are behind schedule on the Gantt chart.

One way to set-up a Primavera P6 layout to highlight activities are behind schedule when compared against their baseline finish dates on the Gantt chart.

The blog post for this video can be found at https://www.plannersplace.com/blog/hi...

Please subscribe to this channel for tips on project planning and scheduling, Primavera P6 and Microsoft Project. Check out my blog, https://www.plannersplace.com/ for more tips & tutorials #primaverap6 #primavera #p6 #projectplanner #projectscheduler #planningengineer.