Chahar Bagh Development Update #43

Описание к видео Chahar Bagh Development Update #43

Discover the Latest in Chahar Bagh Development!

Our dedication to excellence is reflected in the most recent infrastructure progress report:
-Earth Work: 99.79%
-Pavement: 32.76%
-Drainage: 100%
-Ancillary Work: 20.76%
-Sub-Base & Base Course: 74.23%
-Overhead Water Tank: 85.77%
-Sewerage: 99.8%
-Tubewell: 67.5%
-Water Supply: 82.84%
-Boundary Wall: 92.37%
-Overall Progress: 75.19%



Every percentage represents a significant step toward building a future-ready society. Join us on this transformative journey!

#RUDA #ChaharBagh #Infrastructure #Development