Blue line | ORR METRO | K R Puram to Silkboard FEB 2024 Updates

Описание к видео Blue line | ORR METRO | K R Puram to Silkboard FEB 2024 Updates

Blue line | ORR METRO | K R Puram to Silkboard junction FEBRUARY 2024 Updates

Phase 2A - Silk Board to K R puram & upto Baiyappanahalli Depot - 19.603 KM
ಬಿಎಂಆರ್‌ಸಿಎಲ್ | ಸಿಲ್ಕ್ ಬೋರ್ಡ್‌ ಜಂಕ್ಷನ್‌ನಿಂದ ಕೆ.ಆರ್‌.ಪುರ | ಒಆರ್‌ಆರ್‌ ಮೆಟ್ರೊ

***********************************************
FEBRUARY 2024 Updates

Recorded Date : 04-FEB-2024

Civil Contractor :
PKG1 - AFCONS Infra - 9.859 KM & 2.84 KM of loops and ramps of SB Junction improvement
PKG2 - Shankaranarayana Constructions PVT ltd - 9.744 KM

ಸಿಲ್ಕ್‌ ಬೋರ್ಡ್‌ನಿಂದ ಕಾಡುಬೀಸನಹಳ್ಳಿಯವರೆಗಿನ ಪ್ಯಾಕೇಜ್‌ -1 ನಿರ್ಮಾಣ ಗುತ್ತಿಗೆಯನ್ನು ಆಫ್ಕಾನ್ಸ್‌ ಸಂಸ್ಥೆ ಪಡೆದಿದ್ದರೆ,
ಕಾಡುಬೀಸನಹಳ್ಳಿಯಿಂದ ಬೈಯಪ್ಪನಹಳ್ಳಿಯವರೆಗಿನ ಎರಡನೇ ಪ್ಯಾಕೇಜ್‌ನ ಗುತ್ತಿಗೆಯನ್ನು ಶಂಕರನಾರಾಯಣ ಕನ್‌ಸ್ಟ್ರಕ್ಷನ್‌ ಪಡೆದಿದೆ.

Stations in the stretch :

Central Silk Board Station ( Interchange with Yellow line ) : Pier casting has begun.
HSR layout Station : All pier cast up to concourse level. CC Connector erection in progress
Agara Station : All pier cast up to concourse level.CC Connector erection in progress
Ibbalur Station : All pier cast up to concourse level.
Bellandur Station : Platform level and concourse level arms launching has begun.
Kadubeesanahalli Station : All Piers cast up to concourse level.CC Connector and TL connector erection.
Kodibeesanahalli Station : All pier cast up to concourse level. CC Connector and TL connector erection.
Marathahalli Station : Concourse beam casting in progress.
ISRO Station : All piers cast up to concourse level.CC Connector erection in progress
Doddanekundi Station : All pier cast up to concourse level
DRDO sports complex Station : Concourse arms and track level arms erection in progress
Saraswathi Nagar Station ( Mahadevpura ): Concourse slab casting works in Progress
K R Pura Station ( Interchange with Purple line ) : Concourse beam being cast

#bmrcl #bangaloremetro #ORRMetro