Скачать или смотреть Method Statement of Pile Cap

  • Civil Construction Studio
  • 2024-05-23
  • 258
Method Statement of Pile Cap
footingcolumnbeamMetro railhow to make buildingdrawingdesignFoundationviral video 2024viral video 2023youtube video 2024youtube monetizationaccidentconstruction accidentfacebook viral reeltiktok viral videoyoutube update videoupdate news
  • ok logo

Скачать Method Statement of Pile Cap бесплатно в качестве 4к (2к / 1080p)

У нас вы можете скачать бесплатно Method Statement of Pile Cap или посмотреть видео с ютуба в максимальном доступном качестве.

Для скачивания выберите вариант из формы ниже:

  • Информация по загрузке:

Cкачать музыку Method Statement of Pile Cap бесплатно в формате MP3:

Если иконки загрузки не отобразились, ПОЖАЛУЙСТА, НАЖМИТЕ ЗДЕСЬ или обновите страницу
Если у вас возникли трудности с загрузкой, пожалуйста, свяжитесь с нами по контактам, указанным в нижней части страницы.
Спасибо за использование сервиса video2dn.com

Описание к видео Method Statement of Pile Cap

METHOD STATEMENT OF PILE CAP.
A pile cap is a thick concrete foundation rest on concrete or timber piles that have been driven into soft or unstable ground to provide a stable foundation. It usually forms part of the foundation of a building or structure or it is the uppermost portion of a pile which acts to secure the piles in position and receive and distribute superstructure loads.

In this video we will discuss the method statement of pile cap in detail with the help of following section:

Equipment
Procedure
Safety

Number 1 . EQUIPMENT

Excavator
Dumpers
Batching Plant
Transit Mixers
Truck / trailer
Welding Generator
Concrete Vibrators
Concrete Needles
Jack hammer
Compressor
Crane / Hydra
De-watering Pump
As per site condition above mentioned equipment can be increased or decreased.

Number 2. Procedure

SURVEY:

Before commencing excavation, the pile cap area shall be marked on the ground after carrying out survey with reference to control points. After excavation the levels of the pit shall be checked for correctness to the drawings and recorded. Longitudinal and transverse centerlines shall be marked outside the pit for reference for cross checking the pile.

EXCAVATION:

Shoring shall be provided depending upon the stability of the soil found in the area. Shoring shall be done with the help of old steel plates and props. At road locations the pit shall be excavated to the dimensions providing working space all around the pile cap, to facilitate fixing of steel & erection of shuttering as detailed in the drawings.

REMOVAL OF Pile Head :

After excavation the pile head of the piles shall be removed by using Pneumatic Jack Hammers seven days after casting of pile or manually three days after casting of pile.

PCC:

After leveling the bottom of the bed, sprinkle some water to keep the soil moist. PCC of Mix M15 or specified in drawing shall be mixed at the centralized batching plant at the casting yard and transported to site in transit mixers. The concrete shall directly pour through chutes from three locations, shall be spread and leveled manually to the specified thickness shown in the drawing.

REINFORCEMENT

a) Fabrication: For fabrication of reinforcement, BBS shall be prepared as per the “Good for Construction” drawings. The Reinforcement shall be cut using cutting machines or manually as required and bent at Rebar yard.

b) Fixing of Re-bars:

The re-bars shall be manually fixed into its position as shown in the good for construction drawing. Reinforcement of pile cap shall be lapped with the reinforcement of pile. Cover blocks of same grade of concrete in which these are to be embedded shall be provided at spacing of about 2.0 m c/c to ensure uniform cover as specified in the drawing and tied together with GI binding wire. After fixing the pile cap rebar, pier or column shaft rebar shall be erected. This rebar shall be supported by erecting a suitable staging frame across the width of the pile cap. The rebar, chairs, spacers & laps shall be jointly checked after completion of cage placing.
f.SHUTTERING


g.CONCRETING

The required (M-35) grade concrete shall be produced as per the approved concrete design mix from the centralized batching plant and transported by transit mixers to the pouring location. Before pouring concrete, slump of 80 mm to 130 mm shall be checked at pouring location. The concrete shall be placed by concrete pump /placer boom or by direct chutes. Concrete placing commences from one end to another in cascading manner till completion. The drop height of the concrete should not be more than 1.5 m. The concrete shall be vibrated using 60 mm / 40 mm diameter needle vibrators. Concrete cubes shall be taken for testing of compressive strength as per IRC 21 at pouring location. Concreting should be done in such a way that next layer of concrete should be laid before initial set of concrete of previous layer to avoid cold joints. Regular tamping shall be done during & after concreting operation.

h.CURING



The concrete shall be cured by ponding method. Bunds of cement mortar of lean mix shall be built after the concrete attains final setting time after casting of concrete, these bunds shall be filled with water from approved source. The sides of the pile cap shall be covered with Hessian cloth till back filling is started. Further curing is ensured by keeping the backfill moist with water.

i. BACKFILLING

Immediately after de-shuttering, concrete surface shall be checked jointly and get the approval for backfilling.

Комментарии

Информация по комментариям в разработке

Похожие видео

  • О нас
  • Контакты
  • Отказ от ответственности - Disclaimer
  • Условия использования сайта - TOS
  • Политика конфиденциальности

video2dn Copyright © 2023 - 2025

Контакты для правообладателей [email protected]