PORR Austria: Extension of the S3-Weinviertler Expressway

Описание к видео PORR Austria: Extension of the S3-Weinviertler Expressway

On behalf of ASFINAG, PORR (as part of a consortium) is constructing the 11 km long extension of the S3 - Weinviertler Schnellstraße in a total construction time of 31 months. The included 17 bridge objects will be built in only 18 months. Due to the particularly sedimentation-sensitive loess-loam soil, settlements were pre-produced to ensure that none would occur during the construction phase. Due to the Covid-19 pandemic, work is currently being carried out under increased protective measures, such as the mandatory wearing of mouth and nose protection and additional sanitary containers.