Polavaram Project Delay Telugu: Andhra Pradesh's dream irrigation project was supposed to finish in 2018, then 2022, 2024... now 2027? After 20 years and ₹21,000+ crores spent, only 55% work is complete! This video breaks down the REAL reasons: diaphragm wall failure, cofferdam damage from Godavari floods, quality issues, funding delays, land acquisition battles with Telangana & Odisha, contractor changes, political shifts, and environmental clearances. Learn why this mega project keeps getting delayed and whether 2027 is realistic.
Understand mega projects, civil engineering challenges & governance!
---------------------------------------------------------------------------------------------------------------------------
Upgrade your civil career and become a professional Quantity Surveyor!
👉 Enroll now: https://interest.entri.app/polavaramp...
We provide professional courses in:
Quantity Surveying
Structural Design
---------------------------------------------------------------------------------------------------------------------------
What's in this video:
Polavaram timeline: Start → 2004, promised 2018, delayed to 2022, 2024, now targeting 2027
₹21,000 crores spent but only 55-56% work complete—what went wrong?
Technical failures:
Diaphragm wall collapse—hundreds of crores rebuild, 30% work in 6 months (July-Dec 2025)
Guide bund severe damage—₹100 crore rebuild
Cofferdam failure from 8 lakh cusecs Godavari flood (Aug 2025)—months of work stopped
Engineering complexity: 6 km river diversion, spillways, channels—one mistake = massive damage
Quality & execution issues: International expert suggestions ignored, poor ground-level implementation
Funding problems: Centre reimbursement delays, inflation, design changes, contractors stopped work
Financial vs actual progress: Paper shows 74%, but including land acquisition = only ~50%
Land, legal & political battles: Telangana, Odisha land issues, forest clearances, court cases
Contractor terminations, retendering, government changes: 2019-2024 annual progress just 2.32%, NDA govt 8 months = 6.11%
Environmental & seasonal limits: Monsoon floods stop work every year
Future impact: 7.2 lakh acres irrigation depends on Phase-1, lakhs of farmers waiting
Final lesson: Mega projects need planning + quality + governance + political will—all together!
Question: Will 2027 deadline be realistic? Comment your opinion!
---------------------------------------------------------------------------------------------------------------------------
Why Entri Engineering Jobs Telugu:
We explain mega projects, civil engineering realities, and governance challenges in simple Telugu so you understand what happens behind the scenes!
---------------------------------------------------------------------------------------------------------------------------
For more civil projects analysis, engineering reality checks, and Andhra Pradesh updates, comment, like & subscribe!
#PolavaramProjectTelugu #PolavaramDelayTelugu #AndhraPradeshProjectsTelugu #CivilEngineeringTelugu #MegaProjectsTelugu #GodavariProjectTelugu #IrrigationProjectsTelugu