Cemetery Ridge rehabilitation project time lapse: video #1

Описание к видео Cemetery Ridge rehabilitation project time lapse: video #1

July 11 - August 15, 2016

This time lapse video chronicles the rehabilitation project on Cemetery Ridge. Contractors are now excavating to reestablish Ziegler’s Ravine. Upcoming work includes grading for a commemorative walkway and planting 125 trees to replace the missing area of Ziegler's Grove. In September, park staff will begin working on site rebuilding the Hancock Avenue gate.

If the weather remains fair completion may be in October. If not, it could extend into December. Funding for this project was provided by the Gettysburg Foundation and National Park Service Centennial funds.

For more information about this project please visit our blog: https://npsgnmp.wordpress.com/2015/05...