Grout Silo Removal, S Ext Roofing & Glass Pane Trim Install! 1 July 2024 Giga Texas Update (07:25AM)

Описание к видео Grout Silo Removal, S Ext Roofing & Glass Pane Trim Install! 1 July 2024 Giga Texas Update (07:25AM)

Gigafactory Texas! This is where Model Y’s, and Cyber Truck production happens and soon, the Next Generation Car!

First day of the 3rd Quarter and it was a beautiful day to fly! Most of the work was concentrated on the south end extension area, the east and north sides of the casting machine section of the main factory and the Boring Company tunneling site on the west side of the highway.

Timestamps:
Drone flight overview with discussion & illustration: 0:06 to 2:27
Drone flight footage & infographics: 2:43 to 27:38

In the video introduction, I provide some news and updates on the Cybertruck, particularly the Gray interior, when production of that interior began, a video of a customer delivered gray interior Cybertruck, updates on the Foundation Series production and delivery plans for Tesla (which have recently changed) and more!

On the south end, crews continue to work on the cooling plant on the southeast side, with more exterior cladding installed, work on the ground level machinery and electronics, trenching for the large underground water pipes that will provide the coolant for the plant, and additional work to complete this structure.

On the south side, crews have drained water out of the three underground tunnels and seem to be preparing rebar for the pile caps on top of the tunnel ramps with the screw-type piers. window installation crews were busy near the southwest angled corner installing trim pieces to finish out the glass installation while on the roof, crews were busy installing more insulation on the roof segment above the supercomputer cluster area. This roofing is noticeably of different materials and installation as compared to the rest of the Giga Texas roofing materials and weatherproof membranes.

On the east side of the casting machine section of the main factory, we see crews working on the slab mounts for tanks and equipment on the south side of the steel assembly and on four formed sections for concrete walls on the north end. Further north, crews were buys trenching in the dirt section where storm water pipes and concrete vaults were being installed. concrete forms and rebar have been placed around the south slab to complete the concrete apron.

Thank you for watching and I hope this has been informative, educational, and entertaining for you. If you would like, please consider supporting me via Patreon (link is in the description of this video and in the video itself) so I can continue to make and share these incredible videos.

Follow me on
Patreon   / joeslastchancegarage  
X @JoeTegtmeyer
Instagram (Joe’s Last Chance Garage) for the latest updates: #joeslastchancegarage
Facebook Joe Tegtmeyer and Joe’s Last Chance Garage

Be sure to check out additional Texas Gigafactory footage on these channels:
@Jeff Roberts
@Brad Sloan

Video, photos, illustrations, and commentary on this video is by me, Joe Tegtmeyer unless otherwise annotated.

Music in this video is obtained from the YouTube free and unrestricted and royalty-free use library. Ending song is Mr. Sunny Face - Wayne Jones

Drones used are DJI Mini 2, Mavic Air 2 & Air 3.

Drone flight over Giga Texas is with permission of Tesla and CEO Elon Musk