Sound Transit Link 2 Line Opening Day First Train

Описание к видео Sound Transit Link 2 Line Opening Day First Train

Well, it was supposed to be anyway…The northbound train was the scheduled first trip, but got delayed by ribbon cutting so southbound trains from Redmond ended up leaving first.

Nevertheless, this is the 1st full run between South Bellevue to Redmond Technology station.

The 'starter' 2 line only serves Eastside atm. Connection to Seattle is currently delayed to 2025 due to construction defects.

Scheduled Departure: 11:02AM
Actual Departure: 11:34AM
April 27, 2024

0:00 South Bellevue
3:22 East Main
6:27 Downtown Bellevue
8:00 Wilburton
9:36 Spring District
11:28 BelRed
15:27 Overlake Village
17:17 Redmond Technology