Metro Manila Skyway Stage 3 update as of October 2019

Описание к видео Metro Manila Skyway Stage 3 update as of October 2019

update no. 68 for my documentation of the #MetroManilaSkywayStage3 as we reach the month of October 2019. I have included the at grade dashcam video and the long selfie stick footage plus pictures to indicate some of the progress below. Everyday new developments are happening on this project.
#SkywayStage3
Section 1
1:47 - the gil puyat toll plaza A and B - SB
2:48 - girder installation along Quirino offramp NB-75-79 (as if premier today completed girder installation)
4:02 - see the rebar cage on the staging ground?
4:08 - asphalt continues on the elevated portion NB carriageway

Section 2A
4:21 - Plaza Dilao segment
5:03 - Nagtahan off ramp developments, girder installed on 2 spans
5:48 - Tomas Claudio portion

Section 2B
7:23 - Container Yard developments
9:05 - San Juan river
12:52 - Sm Sta Mesa approach area

Section 3
13:55 - we included pictures of the developments on the NB on ramp
14:20 - Developments on the SB off ramp
14:47 - On and off ramp along Araneta avenue near S3 Pier 67

Section 4
17:43 - there are cars parked above hahaha!
20:17 - delmonte intersection - developments on the girder installation and pier cap erection
21:54 - Sto Domingo Sgt Rivera intersection - from this point girders are being installed, we did some comparison from last months documentation
25:03 - Curve along the Cherrylume property

Section 5
26:05 - Balintawak Interchange
26:50 - Camachile Flyover
28:18 - pile boring activity started along the service road / araneta village area / opposite of eternal gardens

Special thanks to Mr Jerome Sercado for the pictures
If you want to use this video please copy the link on the share button instead of re uploading on another platform. It wont hurt to share the link and it directs the source if you shared the link.
Thank you.

Thank you for watching! see you on the next update!